Wison New Energies signs EPCIC contract for Baleine Phase 3 FPSO

Key highlights
  • Wison New Energies signed the EPCIC contract with Eni and Altera Infrastructure for the Baleine Phase 3 FPSO in Côte d’Ivoire.
  • Wison will continue its involvement from FEED through to EPCIC, covering engineering, procurement, construction, installation and commissioning.
  • The FPSO is designed for 800–1,200 m water depth and to process up to 90,000 barrels of oil per day, 80,000 barrels of produced water per day, and 160 MMSCFD of natural gas.
  • The unit measures approximately 308 m by 57 m by 29.8 m, has a design life of no less than 20 years, and Altera will be the owner/operator.
Related project For subscribers
Milestones, plant data, involved companies (owners, investors, licensors, contractors) and news — kept up to date.
Eni Baleine Phase 3 Expansion, Côte d'Ivoire · Cote D'Ivoire (Ivory Coast)
Under Construction
2026-05-25
2026-07-06
Commissioning & Start-up · expected date for subscribers
—

Contract and partners

Wison New Energies has signed the EPCIC (Engineering, Procurement, Construction, Installation and Commissioning) contract with Eni and Altera Infrastructure for the Floating Production, Storage and Offloading (FPSO) facility for the Baleine Phase 3 offshore oil and gas field in Côte d’Ivoire. Altera Infrastructure is the owner and operator of the FPSO and was previously involved as contractor for redeployment of the FPSO and FSO installed in Baleine Phase 2.

Scope

The contract continues Wison’s involvement from Front-End Engineering Design (FEED) through to EPCIC execution, demonstrating its end-to-end delivery capabilities for global offshore oil and gas development and marking a milestone for Wison in the FPSO sector.

FPSO specifications

The FPSO is designed to operate at water depths of approximately 800–1,200 meters and to process up to 90,000 barrels of oil per day, 80,000 barrels of produced water per day, and 160 MMSCFD of natural gas. The unit will measure approximately 308 meters in length, 57 meters in breadth and 29.8 meters in depth, with a design life of no less than 20 years.

Company statement

Wison New Energies CEO Cheng Yuanyun said the contract “underscores the confidence of international clients in our engineering capabilities, project execution, and supply chain management,” and added that Wison will leverage its mature project management framework and integrated delivery capabilities to ensure the successful execution of the project.

Source: Wison New Energies

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time.

Related articles

26 September 2026
SOCAR signs multiple upstream, LNG and energy-infrastructure agreements

Deals cover a 50/50 PSA for unconventional hydrocarbons, Absheron FID, LNG export options for Haynesville gas, cloud operator appointment and a 10% Baleine stake.

30 July 2026
TechnipFMC Q2 2026 results

Revenue $2.76bn; net income $363m; Subsea inbound $2.5bn; cash from operations $548m and free cash flow $488m; $440m returned to shareholders.

29 July 2026
Eni second-quarter 2026 results and updated capital plan

Double-digit underlying production growth, new JV and project FIDs, entry into critical minerals, and a larger share buyback with slightly higher 2026 production guidance.

27 July 2026
Saipem awarded ~€800m Eni contracts for Ivory Coast offshore and Venice biorefinery

Two awards cover Baleine Phase 3 offshore pipelines and subsea systems, and an EPC deoxygenation unit at the Venice biorefinery to boost HVO output.

6 July 2026
TechnipFMC awarded Eni Baleine Phase 3 subsea contract

Design and manufacture flexible flowlines and risers to tie wells in ~1,200 m water depth to a new floating production unit for a fast‑track expansion offshore Côte d’Ivoire.