MAIRE (Tecnimont) wins ICC Phase 1 award finding EuroChem’s K2 termination wrongful

Key highlights
  • London-seated ICC tribunal confirmed Tecnimont lawfully suspended the K2 contracts because of Western sanctions and is the sole adjudicative body for K2 disputes.
  • The tribunal found EuroChem’s August 2022 termination wrongful and rejected EuroChem’s €1.6 billion counterclaims.
  • EuroChem was ordered to pay Tecnimont and its subsidiary approximately €260 million for costs already incurred under the K2 project.
  • Arbitration moves to Phase 2 to seek a permanent injunction to withdraw Russian proceedings and to decide additional legal costs and damages, with a decision expected in H1 2027.

Arbitral finding

On 28 August 2026 the London-seated arbitral tribunal constituted under the K2 Contracts issued a Partial Final Award (Phase 1 Award) holding that Tecnimont and its subsidiary lawfully suspended performance of the K2 Contracts because of Western sanctions following Russia’s invasion of Ukraine, and that EuroChem’s subsequent termination was wrongful.

Financial outcome

The tribunal found EuroChem liable to pay Tecnimont and its subsidiary approximately €260 million related to costs already incurred for the execution of the K2 project, and dismissed EuroChem’s asserted €1.6 billion counterclaims based on the purported termination.

Jurisdiction and enforcement

The tribunal confirmed it is the sole adjudicative body with jurisdiction over disputes under the K2 Contracts, and held that Russian or other state-court actions initiated by EuroChem in breach of the arbitration agreements may not be recognized or enforced under the 1958 New York Convention.

Next steps

The arbitration will enter Phase 2, in which Tecnimont and its subsidiaries will seek a permanent injunction to compel EuroChem to withdraw the Russian proceedings and will claim legal and other damages; a Phase 2 decision is expected in the first half of 2027.

Background

EuroChem engaged Tecnimont in June 2020 to build the Kingisepp 2 fertilizer plant. Tecnimont suspended the contracts in May 2022 citing EU sanctions; EuroChem purported to terminate them in August 2022, after which Tecnimont began arbitration.

Source: Maire

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time.

Related articles

28 November 2025
MAIRE Challenges EuroChem's Unlawful Actions in UK Court Dispute

MAIRE seeks over €700M in damages, citing EuroChem's contract breaches and contempt of UK court orders, while EuroChem turns to Russian courts, defying arbitration agreements.

21 May 2026
Eni CCUS Holding secures £500m+ financing facility for CCS platform

Facility backs Liverpool Bay CCS (operational 2028; 4.5 Mt/yr rising to 10 Mt by 2030s), funds other projects (L10, Bacton, Ravenna option); 13-bank syndicate; 30% built

17 March 2026
Eni secures €9bn 5-year revolving credit facility

€9bn 5‑year revolver with 2‑year extension option refinancing prior €6bn and €3bn lines; provided by 28 banks, ~40% oversubscription, maintains financial flexibility and extends maturity

13 February 2026
SkyNRG Begins Construction of First SAF Plant in the Netherlands

The plant will produce 100,000 tonnes of SAF annually, cutting GHG emissions by up to 90%. KLM is the main off-taker. Construction follows a seven-year development phase. Completion is due in 2028.

12 February 2026
SkyNRG Begins Construction of Delfzijl SAF Plant

The plant will produce 100,000 tonnes of SAF annually, cutting GHG emissions by up to 90%. KLM is the main off-taker. Construction starts after securing non-recourse project financing.