Carbon Neutral Fuels' Project Starling enters pre‑planning at Workington

Key highlights
  • Carbon Neutral Fuels has signed a Planning Performance Agreement with Cumberland Council to begin formal pre‑planning for Project Starling.
  • Planned output has increased to around 31,000 tonnes of sustainable aviation fuel per year.
  • The facility is expected to support between 100 and 150 skilled jobs in West Cumbria.
  • The project secured £6 million of UK government funding last year and completed engineering milestone FEL3A, enabling further development.
Related project For subscribers
Milestones, plant data, involved companies (owners, investors, licensors, contractors) and news — kept up to date.
Carbon Neutral Fuels Project Starling e-SAF at Workington · United Kingdom
FEED / Pre-FID
2025
2026-05
—
Under Construction · expected date for subscribers
—
Operational / Completed · expected date for subscribers

Progress to pre‑planning

Carbon Neutral Fuels has signed a Planning Performance Agreement with Cumberland Council, marking the start of the formal pre‑planning process for Project Starling. The move follows completion of engineering milestone FEL3A and earlier government support.

Capacity and jobs

Engineering work has increased the planned output to around 31,000 tonnes of sustainable aviation fuel (SAF) per year. Once operational, the plant is expected to support between 100 and 150 skilled jobs in West Cumbria.

Grid connection and stakeholder support

The project is working to secure a timely electricity grid connection; National Grid and Electricity North West will explore innovative ways to connect the site sooner. MP Josh MacAlister has actively pressed ministers on grid delays, helped secure the earlier £6 million backing and continues to raise the project with ministers as the government reviews long‑term SAF policy.

Regional context

Project Starling is presented as part of a growing clean energy investment pipeline in West Cumbria, alongside proposed new nuclear at Pioneer Park and investment in the Port of Workington, which backers say will attract private investment and support local regeneration. Backers note further work is required before construction can begin.

Source: CNF

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time.

Related articles

5 October 2026
Carbon Neutral Fuels seeks community input on Siddick SAF facility

Drop-in on 15 Oct to view early plans for a 40-acre SAF plant at Siddick producing ~42,000 t/yr and creating 500 construction and 150+ permanent jobs.

6 May 2026
Carbon Neutral Fuels' Project Starling completes FEL3A, advancing UK eSAF deployment

FEL3A completed for UK eSAF project: integrated design and 3D model, Class 3 cost estimate. Targets 25,000 tpa by 2031 with ~95% lifecycle GHG reduction; DAC integrated.

19 February 2026
Carbon Neutral Fuels Chooses Johnson Matthey, Honeywell for UK E-Fuels Project

Project Starling will convert CO2 and water into sustainable aviation fuel, aiming for 25,000 tons annually by 2031, using advanced technologies for significant emissions savings.

28 January 2026
Carbon Neutral Fuels and The Carbon Removers to Develop UK Sustainable Aviation Fuel Infrastructure

The partnership aims to scale sustainable aviation fuel, leveraging biogenic CO₂ and infrastructure to meet UK SAF mandates and support long-term decarbonization.

9 December 2025
Topsoe and Carbon Neutral Fuels Collaborate on e-SAF Project with SOEC Technology

Project Starling in the UK will use SOEC technology to produce 25,000 tons of e-SAF annually, aiming for an 89% emissions reduction. Construction starts in 2028, operations by 2031.