SPIE Belgium to integrate 304 MWh battery park in Auvelais

Key highlights
  • Site capacity ~304 MWh able to inject up to 76 MVA into the 150 kV grid for 4 hours.
  • Park will include 82 Megapack-type battery containers and an 82 MVA power transformer.
  • System can supply 30,000–40,000 households for 4 hours or fully recharge 4,000–5,000 electric vehicles.
  • Civil works to run until summer 2026, with contractual commissioning scheduled for end of January 2027; ~14,000 hours of work and up to twenty technicians at peak.

Purpose

The Auvelais battery park will store electricity, notably of renewable origin, produced during surplus periods and return it during consumption peaks to support grid flexibility and integration of intermittent generation.

Capacity and equipment

The site will have a capacity of approximately 304 MWh and can inject up to 76 MVA into the high-voltage grid (150 kV) for four hours. The installation comprises 82 Megapack-type battery containers associated with an 82 MVA power transformer, representing the ability to supply 30,000–40,000 households for four hours or to fully recharge 4,000–5,000 electric vehicles.

SPIE Belgium scope

SPIE Belgium is responsible for the electrotechnical integration: construction of the 150 kV substation, installation and connection of the storage systems, and implementation of all equipment necessary for injecting energy into the grid.

Schedule and workforce

Civil engineering works have begun and will continue until summer 2026, with installation and connection to follow and contractual commissioning scheduled for the end of January 2027. The site represents approximately 14,000 hours of work and will mobilise up to twenty technicians on site at peak activity.

Source: SPIE

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time.

Related articles

31 August 2026
SPIE Belgium to deliver BoP for HybriX Energy’s Volta and Franklin 300 MWh battery parks

Two 150 MWh battery parks tied into Elia's 150 kV network will deliver grid flexibility (70 MW for 4 hours); SPIE handles BoP, HV transformers, SCADA integration and long-term maintenance; commissioning in 2027.

7 May 2026
SPIE Joins Consortium to Build PanTera Actinium‑225 Production Facility in Mol

Consortium to build facility boosting production of a cancer radioisotope; scope includes HVAC, sanitation and technical gases. Construction started; equipment integration planned late 2026.

4 May 2026
SPIE appoints Markus Holzke Group CEO and updates executive committee

Appointment effective after Apr 30, 2026 AGM. Rainer Hollang named CEO for Germany/Switzerland/Austria. Executive committee membership reorganized.

22 April 2026
SPIE renews Johnson & Johnson maintenance contract in the Netherlands and Belgium

3-year renewal for technical facility management at pharmaceutical sites covering maintenance, mechanical engineering, ~€500k/yr energy savings, continuity and expansion support