KMG International expands energy-optimization at Petromidia and Vega refineries

Key highlights
  • Staged measures started on August 5 reduce electrical load by approximately 5 MW during peak periods without affecting refining operations.
  • Petromidia's coking plant rescheduling shifts petroleum coke cutting outside 19:00–23:00, saving about 2.2 MW.
  • Rompetrol Energy's cogeneration plant has ~80 MW capacity, meets platform needs of 60–70 MW and currently delivers 8–10 MW to the national grid during 19:00–23:00; optimization can raise exports by over 50% to more than 13 MW.
  • A planned LDPE unit shutdown from August 22 will cut roughly 8 MW; distribution-level measures include optimizing EV charging and recommending users avoid 19:00–22:00.

Operational measures

KMG International implemented a staged energy consumption optimization programme at the Petromidia and Vega refineries starting August 5 to reduce consumption during peak periods without affecting current activities and technological processes. Measures include optimizing operational programmes, rescheduling activities outside critical intervals and adjusting auxiliary consumption, yielding an approximate 5 MW reduction in electrical load during peaks.

Refinery examples

At Petromidia the petroleum coke cutting operation at the coking plant has been moved outside the 19:00–23:00 critical interval, reducing load by about 2.2 MW while preserving the technological process. All actions are implemented so as not to affect refining and distribution activities; maintaining refineries at optimal operating parameters and high production levels to ensure domestic fuel availability remains the stated priority.

Cogeneration and grid support

Rompetrol Energy's cogeneration plant has roughly 80 MW capacity and supplies the Petromidia platform's estimated 60–70 MW demand depending on regime. Under optimal operation it already delivers between 8 and 10 MW to the national system during 19:00–23:00, and optimisation plus facility investments can increase deliveries by over 50% to more than 13 MW during critical consumption periods, contributing to balancing the Dobrogea network.

Planned shutdown and distribution actions

From August 22 the Low Density Polyethylene (LDPE) unit will enter a planned shutdown after stocks are ensured for customers, enabling an additional reduction of about 8 MW. At the distribution level KMG International is optimising EV charging station use and recommends charging outside 19:00–22:00 to ease network pressure.

Source: Rompetrol Rafinare

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time.

Related articles

9 July 2026
Rompetrol Rafinare Petromidia marks 50-year milestone

50-year anniversary of the Năvodari refinery; built on reclaimed land, now a 29‑unit complex with >5 Mtpa capacity, Nelson Complexity 9.32 and 2025 production records.

13 July 2026
Rompetrol Energy tests island-mode operation at Petromidia cogeneration plant

Plant can start and run without National Energy System power; tested with Transelectrica and Nuclearelectrica; capacity ~80 MWh and 180 t/h steam; can feed surplus to grid.

19 January 2026
Rompetrol Energy's Petromidia Cogeneration Plant Now Operational

The Petromidia cogeneration plant is operational, enhancing energy infrastructure, reducing costs, and supplying electricity and steam to the refinery and National Energy System.