OMV Petrom and ROMGAZ install Neptun Alpha offshore platform in the Black Sea

Key highlights
  • Neptun Alpha platform installed in ~120 m water, weighs 16,500 t and is over 225 m high.
  • Installation used the Saipem 7000 semi-submersible crane vessel and eight seabed piles (>2 m diameter).
  • Six of the 10 development wells and the 160 km onshore pipeline to shore are already completed.
  • Project remains on schedule for start of production in 2027, with subsea pipelines, umbilicals and testing next.

Installation milestone

OMV Petrom and S.N.G.N. ROMGAZ have completed installation of the Neptun Alpha offshore production platform for the Neptun Deep project in the Black Sea, marking a major construction milestone toward first gas in 2027.

Platform specifications and installation

The platform sits in approximately 120 metres of water, weighs 16,500 tonnes and exceeds 225 metres in total height. Saipem fabricated the jacket and topsides in Arbatax (Italy) and Karimun (Indonesia) respectively, and the Saipem 7000 semi‑submersible crane vessel carried out the lift and placement. The jacket was anchored with eight driven piles, each more than two metres in diameter.

Current project status

To date six of the 10 development wells have been completed and the 160 km pipeline to shore has been installed; construction of the Tuzla gas measurement station and control building is advancing. The topsides are fully automated for remote operation and a support vessel (capacity up to 90 people) is being built for operation and maintenance.

Next steps

Work now focuses on drilling remaining production wells, installing and integrating subsea production systems, collector pipelines and umbilicals, connecting offshore facilities to the transport pipeline, and executing a comprehensive testing programme ahead of commissioning for 2027 start‑up.

Source: OMV Petrom 

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time.

Related articles

28 September 2026
OMV Petrom and Romgaz target first gas from Neptun Deep in H1 2027

First gas into Romania's NTS expected H1 2027; plateau by end‑Q3 2027 at ~8 bcm/year; development capex ~EUR 4bn; recoverable volumes ~100 bcm.

4 May 2026
OMV Petrom & ROMGAZ begin Neptun Deep pipelaying in the Black Sea

Pipelaying begins for 160 km Neptun Deep subsea gas line; Castoro 10 on site. ~50-vessel mobilization; subsea systems, platform and wells targeted to deliver first gas in 2027

21 January 2026
BEH Joins Han Asparuh Exploration Venture

BEH acquires 10% in Han Asparuh offshore venture. Exploration drilling began in Dec 2025. Potential economic benefits include GDP growth and enhanced energy security for Bulgaria.

15 December 2025
OMV Petrom Begins Offshore Exploration in Bulgaria's Han Asparuh Block

Exploration drilling in Bulgaria's Han Asparuh block starts with two wells, costing €170M, using advanced tech and safety standards, aiming to enhance regional energy security.

10 December 2025
OMV Petrom Advances Romania's Energy Security

Neptun Deep progresses for 2027 gas. Anaconda-1 drilling follows. Onshore exploration continues. Production licenses extended 15 years.