Mirka and Adven to process 5,000 tonnes of abrasive waste annually

Key highlights
  • Adven will invest in a rotary kiln at Mirka’s site in Jeppo, Finland.
  • The system is designed to process about 5,000 tonnes of coated abrasive waste annually.
  • Recovered heat will support production, and ash containing abrasive grains will go to Mirka’s adjacent recycling plant.
  • The companies plan to expand Mirka’s take-back model for used abrasives across Europe.

Rotary kiln investment

Adven will invest in a dedicated rotary kiln at Mirka’s site in Jeppo, Finland, to treat coated abrasive waste from Mirka’s manufacturing operations and customers. The system is designed to process approximately 5,000 tonnes annually.

The kiln will recover heat for use in production and create an ash stream containing abrasive grains for further processing. The ash will be transferred automatically to Mirka’s adjacent circular grain manufacturing plant.

Further circularity plans

Alongside the investment, the companies have agreed to continue developing circular technologies for the abrasives industry. Plans include expanding Mirka’s take-back model to collect used abrasives from end customers across Europe.

Mirka expects its wider circular grain manufacturing initiative to reduce its CO2 footprint by approximately 5,000 tonnes.

Source: Adven

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time. See our Privacy Policy.

Related articles

23 November 2026
Nobian and Adven receive permits for electric caustic soda installation

The project is expected to cut energy use for evaporation by about 85% and avoid up to 25,000 tonnes of CO₂ emissions annually.

3 September 2026
ORLEN launches Baltic Energy Initiative with 13 regional partners

Regional platform mobilises 14 organisations to coordinate offshore wind, LNG/bioLNG, hydrogen, CCS, SMRs and infrastructure protection across the Baltic Sea region.