Eni and Argentina discuss Argentina LNG FLNG development

Key highlights
  • Argentina President Javier Milei met Eni CEO Claudio Descalzi to discuss energy cooperation and investments.
  • Argentina LNG is a joint project by Eni, YPF and XRG to exploit Vaca Muerta resources using FLNG solutions.
  • An investment decision for the project is expected by the end of the year; initial phase envisages 12 MTPA from two 6 MTPA FLNG units.
  • Start-up of production is planned for 2030 and a subsequent expansion to 18 MTPA is under evaluation.

Meeting overview

The President of the Republic of Argentina, Javier Milei, met with Eni Chief Executive Officer Claudio Descalzi in Paris during events tied to Argentina Week to discuss cooperation in the energy sector and investment opportunities focused on gas development.

Argentina LNG project

The parties reviewed the Argentina LNG project, developed by Eni together with YPF and XRG, which aims to exploit Vaca Muerta resources through floating liquefaction (FLNG) solutions. The project's initial phase envisages production of 12 million tonnes per year via two 6 MTPA FLNG facilities.

Timelines and scale

An investment decision for the project is expected by the end of the year, with production start-up planned in 2030. A potential subsequent expansion to 18 MTPA is currently under evaluation.

Strategic intent

The meeting reaffirmed intentions to strengthen the country’s role in international energy markets and to support growth of energy exports, with implications for European supply security.

Source: Eni

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time.

Related articles

1 October 2026
XRG backs Argentina's push to become global LNG supplier

Argentina targets global LNG supply; first phase 12 Mtpa from Vaca Muerta with YPF and Eni partnership, promising over 40,000 jobs and export revenues.

14 August 2026
Argentina LNG (YPF, Eni, XRG) applies for RIGI approval

Seeks RIGI status to enable an integrated LNG export chain using Vaca Muerta gas, with two FLNG units totalling 12 MTPA offshore Río Negro; FID targeted end‑2026.

29 June 2026
Eni takes 32% stake in Vaca Muerta blocks for Argentina LNG

Acquires 32% of three Vaca Muerta blocks to feed 12 MTPA LNG capacity via two 6 MTPA floating units; deal completion subject to regulatory approvals.

29 June 2026
XRG to acquire 32% upstream stake in Vaca Muerta for ARGENTINA LNG

Acquisition alongside YPF and Eni to supply an integrated 12 MTPA ARGENTINA LNG project; deal needs regulatory approvals and covers three Vaca Muerta blocks.

26 February 2026
Eni Reports Strong 2025 Financial and Strategic Progress

Strong Q4 results with 35% net income growth. Major projects launched, production up 7%. LNG expansion, biofuels growth, and strategic partnerships enhance resilience and shareholder returns.