ESE and Nordic Ren-Gas Partner on €100M Hydrogen Project in Mikkeli

Key highlights
  • The project involves a €100 million investment in a Power-to-Gas facility in Mikkeli.
  • The facility will have an electrolysis capacity of over 40 megawatts, producing renewable methane and hydrogen.
  • Phase one, with a 20 MW electrolyser, is set for completion by 2026, and phase two by 2030.
  • The feasibility study begins in February 2022, with construction starting in 2023.
Related project For subscribers
Milestones, plant data, involved companies (owners, investors, licensors, contractors) and news — kept up to date.
Ren-Gas Mikkeli 40 MW Hydrogen e-Methane · Finland
Under Construction
2022
2026
—
Operational / Completed · expected date for subscribers

Project Overview

Etelä-Savon Energia Oy and Nordic Ren-Gas Oy have signed a cooperation agreement to conduct a feasibility study for a Power-to-Gas facility in Mikkeli. This facility aims to produce renewable methane and green hydrogen, contributing to the hydrogen economy and Ren-Gas's clean gas production network.

Technical and Economic Feasibility

The study will assess the technical and commercial viability of the Power-to-Gas plant at the Pursiala power plant site. The project, valued at over €100 million, may be implemented in phases, with the first phase expected to be completed by 2026 and the second by 2030.

Facility Specifications

The planned facility will have an electrolysis capacity exceeding 40 megawatts, producing synthetic methane to replace approximately 18 million liters of fossil fuel in heavy transportation. This amount corresponds to the annual fuel consumption of 600 heavy trucks in Finland.

Project Development

Nordic Ren-Gas Oy will lead the feasibility study, focusing on developing and owning Power-to-Gas production facilities and distributing renewable transportation fuels. The study will begin in February 2022, with construction of the first phase starting in 2023.

Environmental Impact

The project supports Etelä-Savon Energia's carbon neutrality goals by providing carbon dioxide-free district heating through waste heat reuse. By 2030, almost 40% of ESE's district heat could be produced cost-effectively with waste heat, making the company carbon negative.

Source: ren-gas.com

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time.

Related articles

17 September 2026
Ren‑Gas signs H2PPAs with Helen and second supplier for Tampere e‑methane plant

Long-term H2PPAs secure physical renewable power and Guarantees of Origin for RFNBO-compliant hydrogen, enabling flexible e‑methane production and advancing the project's FID.

10 September 2026
Nordic Ren-Gas selects technology partners for Tampere e-methane plant

Integrated technology chain will turn renewable electricity and captured biogenic CO2 into e‑methane, using electrolysis, methanation, hydrogen handling and waste-heat recovery to district heating.

3 September 2026
EIB raises financing framework for Nordic Ren‑Gas to EUR 680m

E‑methane and green hydrogen projects in Finland to receive EIB support; Tampere site targeted to start construction in Q4 2026.

22 July 2026
Nordic Ren‑Gas and Sunfire agree long‑term electrolysis partnership

Preferred‑supplier agreement secures electrolyzer technology for green hydrogen and e‑methane projects, reinforcing Tampere deployment and pipeline scale‑up.

10 July 2026
Nordic Ren-Gas and avanca/Alternoil sign €1bn renewable e‑methane offtake

Long-term €1bn offtake secures Tampere-produced e‑methane for heavy-duty transport via existing gas/LNG infrastructure across Europe.