Viva Energy Geelong refinery alkylation-unit fire — update

Key highlights
  • Fire occurred in the refinery’s Alkylation unit, part of the Gasoline complex.
  • Emergency response contained the fire, which was fully extinguished by late Thursday morning; all onsite personnel accounted for.
  • Geelong Refinery expects diesel and jet fuel production at approximately 80% capacity and petrol at approximately 60%, and says it has sufficient stocks to cover reduced output.
  • Company expects to lift production above 90% within the next few weeks subject to plant inspections and will conduct a full investigation into the cause.

Incident and response

Viva Energy confirms the fire broke out late on Wednesday in the refinery’s Alkylation unit, part of the broader Gasoline complex. The refinery’s emergency response team, Fire Rescue Victoria and emergency services contained the fire, which was fully extinguished by late Thursday morning. Every person onsite has been safely accounted for.

Operational impact

Most major processing units were unaffected. Following the incident, the Geelong Refinery expects to be producing diesel and jet fuel at approximately 80% of capacity and petrol at approximately 60%. The Company states it has sufficient fuel stocks to cover this reduced production and expects to maintain normal fuel supply.

Recovery and investigation

Subject to plant inspection, the Company expects to be in a position over the next few weeks to lift production of diesel, jet fuel and petrol to over 90% of capacity. Viva Energy’s CEO said the company is committed to conducting a full investigation into the cause of the fire and will progressively restore production once it is confident it is safe to do so.

Source: Viva Energy

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time.

Related articles

30 July 2026
Viva Energy and Cleanaway: NGERs reform recognises co‑processed low‑carbon fuels

Australia’s NGERs now let eligible co‑processed renewable diesel, LPG and kerosene be reported with zero Scope 1 emissions for the biogenic portion, supporting local feedstock use and refinery production.

6 July 2026
Viva Energy opens SAF storage and blending hub at Brisbane Airport

Dedicated end-to-end SAF tank and blending facility now linked to Brisbane Airport JUHI, with certification, carbon-credit integration and digital mass-balance tracking.

30 September 2026
Honeywell Technologies to supply process tech for Dangote’s 700,000 b/d single‑train Kenya refinery

700,000 b/d single‑train refinery in Kenya to come online faster by reusing proven designs, cutting development time by nearly two years; will make fuels and polypropylene and handle varied crudes.

8 September 2026
Exolum August 2026 deliveries to Spain down 0.3% y/y

Total outflows 3.7 million cubic metres; gasoline +6.7%, diesel -3.5%; motor fuels 2.5 million m³ (-0.1%); kerosene 868,700 m³ (+4.8%).

14 August 2026
Rompetrol Rafinare posts solid H1 2026 results

Consolidated turnover +25% to USD 3.5bn; EBITDA +65% to USD 128.1m and net profit USD 40.4m. Petromidia shifted output toward domestic market; H2 outlook cautious.