Engen-led consortium outlines Durban LNG-to-power plans
- The project includes an LNG terminal with peak regasification capacity of about 5 billion cubic metres a year.
- Construction is expected to start in late 2028, subject to approvals and a final investment decision; operations are targeted for H2 2031.
- VTTI would develop and operate the terminal and pipelines, Vitol would supply LNG, and Acwa would develop the power plant.
- The consortium is targeting about 30% ownership by South African B-BBEE partners.
Project scope
The proposed ZAR 40 billion development would include an LNG import terminal at the Port of Durban, pipeline infrastructure and a 1.9 GW combined-cycle gas turbine power plant at the former Engen refinery site. The plant is expected to generate enough electricity for the equivalent of about 3.9 million households. The terminal would have peak regasification capacity of about 5 billion cubic metres a year.
Partners and timeline
VTTI would develop and operate the terminal and pipelines, Vitol would supply LNG, and Acwa would develop the power plant. The consortium is targeting about 30% ownership by South African Broad-Based Black Economic Empowerment partners. Construction is expected to begin in late 2028, subject to a final investment decision and local approvals; operations are targeted for the second half of 2031.
Supply and economic impact
The terminal is intended to help offset an anticipated decline in pipeline gas imports from Mozambique and supply both the power plant and industrial users. The project could support about 4,500 person-years of employment during construction and around 740 ongoing jobs, including about 220 direct positions. Preliminary estimates put construction’s contribution to South African GDP at about ZAR 26 billion and annual operational contribution at about ZAR 1.8 billion. The project could also generate more than ZAR 245 million a year in throughput-related revenue for the Port of Durban and enable LNG bunkering services.
Approvals
Development remains subject to participation in South Africa’s second Gas-to-Power procurement round, regulatory and environmental approvals, and other project milestones.
Source: Vitol