Engen-led consortium outlines Durban LNG-to-power plans

Key highlights
  • The project includes an LNG terminal with peak regasification capacity of about 5 billion cubic metres a year.
  • Construction is expected to start in late 2028, subject to approvals and a final investment decision; operations are targeted for H2 2031.
  • VTTI would develop and operate the terminal and pipelines, Vitol would supply LNG, and Acwa would develop the power plant.
  • The consortium is targeting about 30% ownership by South African B-BBEE partners.
Related project For subscribers
Milestones, plant data, involved companies (owners, investors, licensors, contractors) and news — kept up to date.
Engen-led Durban LNG import terminal and 1.9 GW CCGT power project · South Africa
Announced / Concept
2026-02-16
—
—
Under Construction · expected date for subscribers
—
Operational / Completed · expected date for subscribers

Project scope

The proposed ZAR 40 billion development would include an LNG import terminal at the Port of Durban, pipeline infrastructure and a 1.9 GW combined-cycle gas turbine power plant at the former Engen refinery site. The plant is expected to generate enough electricity for the equivalent of about 3.9 million households. The terminal would have peak regasification capacity of about 5 billion cubic metres a year.

Partners and timeline

VTTI would develop and operate the terminal and pipelines, Vitol would supply LNG, and Acwa would develop the power plant. The consortium is targeting about 30% ownership by South African Broad-Based Black Economic Empowerment partners. Construction is expected to begin in late 2028, subject to a final investment decision and local approvals; operations are targeted for the second half of 2031.

Supply and economic impact

The terminal is intended to help offset an anticipated decline in pipeline gas imports from Mozambique and supply both the power plant and industrial users. The project could support about 4,500 person-years of employment during construction and around 740 ongoing jobs, including about 220 direct positions. Preliminary estimates put construction’s contribution to South African GDP at about ZAR 26 billion and annual operational contribution at about ZAR 1.8 billion. The project could also generate more than ZAR 245 million a year in throughput-related revenue for the Port of Durban and enable LNG bunkering services.

Approvals

Development remains subject to participation in South Africa’s second Gas-to-Power procurement round, regulatory and environmental approvals, and other project milestones.

Source: Vitol

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time. See our Privacy Policy.

Related articles

27 February 2026
PETRONAS Reports Lower Profit Amid Market Challenges, Focuses on Long-Term Value

Revenue and profit decreased due to lower prices and sales. PETRONAS prioritizes resilience and strategic growth amid ongoing market volatility and geopolitical challenges.

29 October 2025
Sumitomo Corporation Secures Financing for Uzbekistan's Largest Solar and Battery Project

The project will generate 1,000 MW of solar power and 1,336 MWh of storage, supporting Uzbekistan's energy transition with a 25-year power purchase agreement. Completion is expected post-2027.

1 September 2026
Veolia signs three MOUs with Saudi partners on desalination, mining water reuse and LPG decarbonisation

Three MOUs with Saudi industrial partners target desalination efficiency, mining water and waste reuse, and decarbonisation of LPG storage, with potential CO2 savings of 500,000 t/yr.

27 January 2026
Topsoe Supports Saudi Arabia's Green Ammonia Project

Topsoe's technology will enable green ammonia production in Saudi Arabia, reducing CO2 emissions by 1.7 million tons annually, with operations expected to start in 2030.

27 January 2026
Topsoe Supports Saudi Arabia's Green Ammonia Project

Topsoe's technology will enable green ammonia production in Saudi Arabia, reducing CO2 emissions by 1.7 million tons annually, with operations expected to start in 2030.