Arq commissions first granular activated carbon line at Red River Plant

Key highlights
  • Completed commissioning of Arq’s first Granular Activated Carbon (GAC) production line at the Red River Plant and commenced ramp-up.
  • Initial production achieved and first GAC shipments sold to customers for testing programs.
  • Targeting full nameplate capacity of 25 million pounds annualized within the next six months.
  • Will begin fulfilling existing supply agreements and is finalising contract negotiations for remaining Phase One capacity; next expansion stage contingent on ramp-up and contracting.
Related project chemXplore Alpha
Milestones, plant data, involved companies (owners, investors, licensors, contractors) and news — kept up to date.
Arq Red River Plant First GAC Production Line Expansion · United States
On Hold / Postponed
2023-10-23
2024-01-24
2024
2025-08-06
2026-03

Commissioning and ramp-up

Arq has completed commissioning of its first Granular Activated Carbon (GAC) production line at the Red River Plant and has formally moved the facility into ramp-up. Initial production was achieved in recent weeks and operations are now focused on optimising processes to reach nameplate capacity.

Production targets and commercial activity

Management anticipates the plant will reach its full nameplate capacity of 25 million pounds annualized within the next six months. The company reports first sales revenue from initial GAC shipments to customers for previously announced testing programs and will begin fulfilling existing supply agreements as production increases.

Contracts and next steps

Arq is finalising contract negotiations for remaining Phase One production capacity. The company says once ramp-up and contracting milestones are achieved it will be prepared to develop the next stage of its GAC expansion.

Source: arq.com