Aibel wins FEED contract for Wisting production-vessel topsides

Key highlights
  • Aibel awarded the FEED contract for the production-vessel topsides at Wisting.
  • Approximately 250 people will be involved in the study.
  • Scope covers FEED and design maturation with an option for engineering, procurement and project management (EPma); topside fabrication will be contracted later.
  • Wisting partners: Equinor (42.5%), Aker BP (27.5%), Petoro (20%) and INPEX Idemitsu Norge (10%); concept selection by end‑2026 and investment decision planned for late‑2027.
Related project For subscribers
Milestones, plant data, involved companies (owners, investors, licensors, contractors) and news — kept up to date.
Equinor Wisting Oil Field Development (FPSO), Barents Sea, Norway · Norway
FEED / Pre-FID
2021-11-10
FID / Sanctioned · expected date for subscribers
—
—
—

Contract award

The Wisting partnership has awarded Aibel a front-end engineering and design (FEED) study contract for the production-vessel topsides following a competitive tender among Norwegian suppliers.

Scope and resourcing

The contract covers front-end engineering and further maturation of the topside design to provide the basis for a project execution decision, and includes an option for engineering, procurement and project management (EPma). Aibel says about 250 people will be involved. Fabrication of the topside modules will be awarded at a later stage.

Schedule and partners

The partnership plans a concept selection and a decision on whether to progress Wisting toward the end of 2026, with a planned investment decision in late 2027. Wisting licensees are Equinor Energy AS (42.5%), Aker BP ASA (27.5%), Petoro AS (20%) and INPEX Idemitsu Norge AS (10%).

Source: Equinor

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time.

Related articles

25 June 2026
Equinor submits EIA programme for Wisting development

Public consultation opens on the EIA programme for a possible Wisting FPSO development in the Barents Sea; consultation runs 16 weeks and FID is targeted end-2027.

15 June 2026
Equinor advances Johan Sverdrup phase 4 subsea development

Appraisal wells confirmed 20–30 million boe in Tonjer and Geitungen; planned subsea tie-back to maintain Johan Sverdrup production with possible start-up in 2029.

22 August 2025
ORLEN Discovers Major Oil Reserve in North Sea

A significant oil find in the North Sea, with up to 134 million barrels, advances ORLEN's 2035 Strategy. Advanced drilling tech and geo-steering enhanced exploration success.

8 January 2026
Equinor Awards Major Contracts to Norwegian Suppliers

Equinor's framework agreements, worth NOK 100 billion, aim to enhance operations, create jobs, and boost competitiveness in Norway's offshore and onshore facilities.

3 October 2025
Equinor's Melkøya Fall Incident Investigation

An internal investigation identified multiple factors in a fall accident, prompting safety improvements and enhanced supplier collaboration at onshore facilities.