Equinor submits EIA programme for Wisting development

Key highlights
  • Proposed EIA programme for a possible Wisting field development submitted for a 16-week public consultation.
  • Wisting holds an estimated just under 500 million barrels of oil equivalent recoverable.
  • Partnership selected an FPSO; power-from-shore was ruled out and an energy-efficient gas turbine plus potential CCS are being assessed.
  • Final concept decision planned by end-2026 and a final investment decision targeted for end-2027.

Project and consultation

Equinor and partners have submitted a proposed programme for the environmental impact assessment (EIA) of a possible Wisting field development in the Barents Sea and opened a 16-week public consultation. The project remains at an early stage and further progress depends on additional work to achieve a viable, profitable development.

Field scale and concept

Wisting is described as the largest oil discovery on the Norwegian continental shelf yet to be developed, with estimated recoverable volumes of just under 500 million barrels of oil equivalent. The partnership has selected a floating production and storage vessel (FPSO) as the development solution; the hull cannot be built at Norwegian yards due to size and infrastructure constraints.

Energy, emissions and technology choices

Power from shore was thoroughly assessed but ruled out because of technical complexity and high costs. The project is pursuing an energy-efficient gas turbine solution and will assess the potential for carbon capture and storage (CCS) to reduce CO₂ emissions, contingent on suitable technological and regulatory conditions and acceptable costs and timelines.

Timeline, partners and impacts

Further maturation and sub-studies are ongoing, with final concept selection and possible continuation targeted toward the end of 2026 and a final investment decision planned for the end of 2027. If realised, Wisting would generate substantial revenues and long-term ripple effects for the Norwegian supplier industry, with around 30 years of operations and most activity occurring in Norway. Drilling, wells and subsea work account for about half of total investment. Licensees: Equinor Energy AS (42.5%), Aker BP ASA (27.5%), Petoro AS (20%) and INPEX Idemitsu Norge AS (10%).

Source: Equinor

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time.

Related articles

15 June 2026
Equinor advances Johan Sverdrup phase 4 subsea development

Appraisal wells confirmed 20–30 million boe in Tonjer and Geitungen; planned subsea tie-back to maintain Johan Sverdrup production with possible start-up in 2029.

22 August 2025
ORLEN Discovers Major Oil Reserve in North Sea

A significant oil find in the North Sea, with up to 134 million barrels, advances ORLEN's 2035 Strategy. Advanced drilling tech and geo-steering enhanced exploration success.

5 December 2025
Equinor Discovers Gas and Condensate in North Sea

Two new gas and condensate finds in the Sleipner area can be developed for Europe using existing infrastructure, enhancing export capacity and profitability with minimal environmental impact.

26 August 2026
ORLEN starts production at Idun Nord, Alve Nord and Ørn in Skarv area

Adds ~30 million boe (mostly gas) and >4 billion m³ of gas; tied to Skarv FPSO with 4.5 kg CO2/boe intensity; lifts Skarv output toward 9 million boe by 2027.

24 August 2026
Equinor, Aker BP and Vår Energi form exploration alliance on the Norwegian continental shelf

A joint programme will target high‑impact prospects to find standalone field candidates by testing 20–25 opportunities and drilling about five wells per year.