AFRY to provide EPCM services for Cabaçal mining project

Key highlights
  • The project is in Mato Grosso, Brazil.
  • The processing plant is designed to handle 2.5 million tonnes of ore per year.
  • AFRY will provide engineering, procurement and construction management services.
  • The assignment is expected to run for two years.
Related project For subscribers
Milestones, plant data, involved companies (owners, investors, licensors, contractors) and news — kept up to date.
Meridian Cabaçal Copper-Gold-Silver Mine and Concentrator, Brazil · Brazil
FEED / Pre-FID
2023-12-05
2025-05-08
—
Under Construction · expected date for subscribers
Commissioning & Start-up · expected date for subscribers
Operational / Completed · expected date for subscribers

Project scope

AFRY will provide engineering, procurement and construction management (EPCM) services to Rio Cabaçal Mineração, a subsidiary of Meridian Mining, for the Cabaçal copper, gold and silver mining operation in Mato Grosso, Brazil. The project includes a processing plant with capacity of 2.5 million tonnes of ore per year, plus power, water management, utilities, process facilities and operational structures.

Engineering and construction support

AFRY will review and optimize the basic engineering package, assess constructability and support project execution planning. Its work also includes detailed engineering for the concentrating plant and associated infrastructure, and technical support for procurement.

During construction, AFRY will provide construction management, field engineering, quality assurance, health and safety oversight, and commissioning support. The assignment is expected to run for two years.

Source: AFRY

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time. See our Privacy Policy.

Related articles

2 October 2026
Indaver and Sleco open Doel site for Voka Open Business Day

Public tours show energy-from-waste operations, lamp recycling, bottom-ash recovery and a landfill viewpoint across themed routes with music and family activities.

25 August 2026
Metso to supply ~EUR 25m processing package for Yenipazar polymetallic project

Key concentrator package for a greenfield polymetallic mine in Yozgat province covering comminution, flotation, dewatering and online analytics.

12 August 2026
Boliden: Laver concession upheld after appeals rejected

Government rejected appeals, keeping the Laver concession intact; the deposit could double Sweden’s copper output and boost Europe’s copper self-sufficiency by about 10%.

31 July 2026
Umicore H1 2026 results

Adj. EBITDA +33% to €577m and margin 30.2%; revenues €1.9bn; Free Operating Cash Flow €295m; guidance upgraded to slightly above €1bn adj. EBITDA for FY2026.

16 June 2026
MAIRE/NEXTCHEM buys 70% of ETEK (owner of SISEMTEK) to add metals recovery capabilities

Majority buy adds pyrometallurgical, hydrometallurgical and electrowinning tech to recover precious and critical metals from e‑waste, batteries, PV panels and mining tailings.