- EPC contract covers topside modifications at Ekofisk Complex.
- FEED completed in November; EPC starts January 2026, ends autumn 2028.
- Project involves Albuskjell, Vest Ekofisk, and Tommeliten Gamma fields.
- Contract subject to regulatory approvals.
Project Overview
Worley Rosenberg has secured an Engineering, Procurement, and Construction (EPC) contract for the Previously Produced Fields (PPF) project with ConocoPhillips Skandinavia AS. This follows the completion of the front-end engineering design (FEED) phase.
Scope and Timeline
The EPC contract involves topside brownfield modifications on existing platforms at the Ekofisk Complex on the Norwegian Continental Shelf. The FEED work was completed in November, and the EPC phase is set to commence in January 2026, with project delivery planned for autumn 2028.
Project Details
The PPF project is a joint redevelopment of the Albuskjell, Vest Ekofisk, and Tommeliten Gamma fields, which are tied back to the Ekofisk Complex. The contract is part of an existing Frame Agreement and is contingent upon regulatory approvals.