TechnipFMC awarded flexible-pipe contract for Azule Energy West Hub Tails

Key highlights
  • TechnipFMC will supply flexible flowlines, risers and associated equipment for Azule Energy’s West Hub Tails project, an extension of the Block 15/06 Agogo Integrated Development.
  • The hardware will accommodate all West Hub production for consolidation into the Agogo Floating Production, Storage, and Offloading vessel (FPSO).
  • TechnipFMC defines a “significant” contract as between $75 million and $250 million.
  • The award will be included in TechnipFMC’s inbound orders in the third quarter of 2026.
Related project chemXplore Alpha
Milestones, plant data, involved companies (owners, investors, licensors, contractors) and news — kept up to date.
Azule Energy West Hub Tails Extension, Angola · Angola
FEED / Pre-FID
2026-08-11
2026-08-11

Scope

TechnipFMC will design and manufacture flexible flowlines, risers and associated equipment to accommodate all production from the West Hub area for consolidation into the Agogo Floating Production, Storage, and Offloading vessel.

Value and timing

TechnipFMC classifies the award as "significant," which for the company means a contract between $75 million and $250 million; the award will be included in inbound orders in the third quarter of 2026.

Project context

The contract supports Azule Energy’s West Hub Tails project, an extension of the Block 15/06 Agogo Integrated Development.

Supplier comment

Jonathan Landes, President, Subsea at TechnipFMC, said the company appreciates Azule’s continued trust after two previous phases and that the team is excited to deliver a robust solution with schedule certainty on this fast-track development.