SPIE modernizes electrical infrastructure at Uniper's Staudinger power plant

Key highlights
  • Modernization of block 4 runs from 2024 to 2028 and the plant will remain in service until 2031 per the Federal Network Agency.
  • SPIE will replace approximately 52 km of main low-voltage distribution network cables and remove about 180 tonnes of used copper.
  • All low- and medium-voltage cables will be replaced; low-voltage busbars on four transformers will be converted to cables and 10 kV connections of two service transformers will be refurbished or replaced.
  • In 2024 SPIE retrofitted the generator coupling circuit breaker and replaced frequency converters for feedwater pumps, laying about 35 km of medium/low-voltage and control cables.
Related project For subscribers
Milestones, plant data, involved companies (owners, investors, licensors, contractors) and news — kept up to date.
Uniper Staudinger Block 4 Electrical Modernization · Germany
Under Construction
2024
—
Operational / Completed · expected date for subscribers

Overview

SPIE is modernizing the electrical and control‑command installations of block 4 at the Staudinger gas-fired power plant in Großkrotzenburg. The program began in 2024 and is due for completion in 2028, delivering technical foundations for safe, reliable long-term operation. The Federal Network Agency classifies the plant as essential to grid stability and security of supply, and it will therefore remain in service until 2031.

Scope of works

Works cover replacement of low-voltage switchgear and the installation, connection and dismantling of electrical equipment and control systems. SPIE will completely replace all low- and medium-voltage cables, replace low-voltage busbars on the low-voltage side of the four existing low-voltage transformers with cables, and refurbish or replace the 10 kV connections of two service transformers. Where parts of the installation must stay live, new cable trays will be laid parallel to existing routes; cable pulling and substation control‑system services are included.

Key figures and recent activity

The project includes replacing the main low-voltage distribution network cables over a distance of approximately 52 kilometres and the removal of 180 tonnes of used copper. In 2024, SPIE also supported retrofitting of the generator coupling circuit breaker and replacement of frequency converters for the feedwater pumps, laying and connecting roughly 35 kilometres of medium, low‑voltage and control cables.

Source: SPIE

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time.

Related articles

1 July 2026
SPIE acquires Swiss life‑sciences engineering firm nimeg ag

Strengthens Swiss GMP/EPCMV engineering capability to deliver EPC projects as general contractor for pharma, biotech and medical‑device clients; nimeg reported ~€5m revenue in 2025.

4 May 2026
SPIE appoints Rainer Hollang General Manager for Germany, Switzerland and Austria

Rainer Hollang becomes GM for Germany, Switzerland & Austria (effective May 1, 2026). He joins the group executive committee reporting to Markus Holzke; civil engineer with a long internal career since 2005.

4 May 2026
SPIE appoints Markus Holzke Group CEO and updates executive committee

Appointment effective after Apr 30, 2026 AGM. Rainer Hollang named CEO for Germany/Switzerland/Austria. Executive committee membership reorganized.