thyssenkrupp Polysius pre-engineers SMA Mineral 120 t/d EAC pilot in Mo i Rana

Key highlights
  • thyssenkrupp Polysius is executing pre-engineering for a 120 t/d Electric Arc Calciner (EAC) pilot plant in Mo i Rana, Norway.
  • SMA Mineral commissioned the work and SaltX Technology's EAC process will be integrated.
  • Design scope targets a multi-stage cyclone preheater with cyclone-flash cooling for preheating and cooling.
  • SMA Mineral funded material tests, supported by SaltX, to validate thermal behavior and inform the FEED.

Project and scope

thyssenkrupp Polysius was commissioned by SMA Mineral to perform pre-engineering for a flash calcination pilot using SaltX Technology’s Electric Arc Calciner (EAC) at Mo i Rana, Norway; the FEED-level work focuses on conceptual design and preliminary layout of preheating and cooling systems for a planned 120 t/d pilot.

Technical solution

Engineering targets a multi-stage cyclone preheater with cyclone-flash cooling adapted to site structural conditions and integrates the EAC process; the pre-engineering provides the technical basis for the pilot and potential future full-scale facility.

Material tests and next steps

SMA Mineral financed material tests, supported by SaltX, to assess thermal behavior inside the cyclone preheater under electric process conditions; test data will validate and refine key process parameters and feed into the FEED, supporting the ZEQL project goal of moving quicklime production toward fully electric, low-emission operation.

Source: thyssenkrupp Polysius

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time.

Related articles

15 December 2025
thyssenkrupp Polysius Aids SMA Mineral in EAC Pilot Plant Design in Norway

Developing a pilot plant for electric arc calcination to boost lime production efficiency, reduce emissions, and enhance Nordic industry resilience.

4 August 2025
thyssenkrupp Polysius to Supply Electric Kiln for Zero-Emission Lime Plant

The project uses SaltX tech for CO2-free lime production, with a 2027 completion target and 40,000-ton capacity, backed by EUR 24M from Enova.

15 December 2025
thyssenkrupp Polysius Aids SMA Mineral in EAC Pilot Plant Pre-Engineering

Developing a flash calcination plant in Norway, focusing on preheating and cooling systems, to enhance lime production efficiency and reduce emissions.

13 May 2026
thyssenkrupp Polysius spins off sustainable process technologies into thyssenkrupp Calvion

Effective 1 May 2026, a carve‑out bundles Oxyfuel and other CO₂‑reduction process technologies into a dedicated unit to speed development, industrialization and market deployment for heavy industries.

15 December 2025
thyssenkrupp Polysius and SaltX Collaborate on Emission-Free Facilities

The partnership aims to develop electrified production facilities using Electric Arc Calciner technology for emission-free processes in cement, lime, and CO2 capture.