INPEX awards McDermott–Baker Hughes consortium Ichthys subsea contract

Key highlights
  • The contract covers engineering, procurement, construction, installation and commissioning of new subsea infrastructure.
  • Project management will be based in Perth, with engineering in Kuala Lumpur and Chennai.
  • Fabrication is planned at McDermott’s facility in Batam, Indonesia.
  • Ichthys offshore facilities are about 220 km off Western Australia.

Contract scope

INPEX awarded McDermott and Baker Hughes a contract for the next phase of the Ichthys LNG development offshore Western Australia. Under their existing Subsea Development Framework Agreement, the consortium will engineer, procure, construct, install and commission subsea infrastructure tied to the existing offshore production system.

Project locations

Project management will be based in Perth, Australia. Engineering work will also be carried out in McDermott’s offices in Kuala Lumpur, Malaysia, and Chennai, India. Fabrication will take place at its facility in Batam, Indonesia.

Ichthys LNG’s offshore production facilities are in the Browse Basin, about 220 km off the north-west coast of Western Australia.

Source: McDermott

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time. See our Privacy Policy.

Related articles

19 November 2025
Aramco Announces $30bn in New US Agreements

Aramco's new agreements focus on LNG, financial services, advanced materials, and procurement, enhancing strategic growth and US partnerships.

8 September 2026
McDermott wins subsea contract for Cronos gas field, Cyprus

Valued at USD $500–$750M, the deal covers project management, engineering, procurement and installation support, executed from hubs in Houston, Perth, London and Kuala Lumpur.

24 August 2026
McDermott awarded ADNOC Package 4 EPCI for Umm Shaif SPB project

EPCI covers a new surface pressure boosting facility with jacket, topside and brownfield work; engineering led from the UAE; fabrication at Qingdao JV yard; contract exceeds $1bn.

7 August 2026
Saipem (SMDC) signs LOI for Rovuma LNG Phase 1 onshore midstream

LOI covers $32M for preliminary engineering and procurement to advance project definition; final EPC award depends on FID and government/regulatory approvals expected in 2026.

6 August 2026
ExxonMobil awards McDermott LOI for Rovuma LNG Phase 1 engineering

LOI covers limited engineering and procurement to advance project definition toward a 2026 FID; Phase 1 targets 18.6 mtpa from 12 modular trains with start-up in 2031.