KBR advances Woodside Pluto Train 1 modifications

Key highlights
  • Modifications will enable the existing Train 1 to process up to 3 million tonnes per annum of Scarborough gas.
  • Scope includes installation of an NGL Unit, a Nitrogen Recycle Compressor, gas custody metering systems and upgrades to supporting facilities within the existing footprint.
  • Work has progressed since September 2023 across detailed engineering, procurement and construction while operating inside an active LNG facility.
  • In 2025 KBR completed a major module deck lift at Laem Chabang and delivered/installed the 4,600 tonnes‑equivalent NGL North Module for hook‑up.
Related project For subscribers
Milestones, plant data, involved companies (owners, investors, licensors, contractors) and news — kept up to date.
Woodside Pluto Train 1 Scarborough Modifications
Under Construction
2021-11-22
2023-09-01
—
Operational / Completed · expected date for subscribers

Project overview

Since September 2023 KBR has been executing the Pluto Train 1 Scarborough Modifications Project to enable the existing Train 1 facility to process up to three million tonnes per annum of gas from the Scarborough Energy Project through modifications to existing plant and associated infrastructure.

Scope and technical challenges

The brownfield scope covers installation of a Natural Gas Liquids (NGL) Unit, a Nitrogen Recycle Compressor, gas custody metering systems and a range of supporting‑facility upgrades, all within the current Pluto LNG footprint. The work combines brownfield execution, modular construction and integration within an operating LNG facility.

Progress and milestones

KBR and Woodside have advanced detailed engineering, procurement and construction while maintaining a focus on safety, quality and execution certainty. A key milestone in 2025 was the first major module deck lift at the Laem Chabang fabrication yard in Thailand, part of the largest of three fabrication modules. The project has since delivered and installed the 4,600 tonnes‑equivalent NGL North Module, and hook‑up work to tie the module into Train 1 has commenced.

Delivery approach and local participation

KBR reports using an integrated delivery model to coordinate global teams and support execution, while the project’s supply chain and industry participation initiatives create opportunities for Western Australian businesses, Indigenous suppliers and local communities.

Source: KBR

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time.

Related articles

14 May 2025
Aramco Signs 34 MoUs with US Firms

Aramco's $90B MoUs target LNG, chemicals, AI, and more, enhancing shareholder value and fostering innovation with US partners.

16 March 2026
OCI Global H2 and FY 2025 Unaudited Results

Geopolitical tensions raise gas costs, impacting nitrogen production. OCI divests assets, plans merger with Orascom. Court halts shareholder vote pending inquiry. Revenue and EBITDA decline.

6 October 2026
KBR wins Aramco Marjan offshore engineering contract

Engineering and execution for offshore processing, gas compression and power upgrades; focuses on sustaining production, improving associated gas processing and adding digital and automation capabilities.

28 September 2026
OCI Global H1 2026 results and strategic progress

Net profit USD 1m; sold ammonia distribution and monetized Methanex; OCI Nitrogen impaired and facing margin pressure; held‑for‑sale net cash USD 1.05bn; NNS offer and Orascom deal progressing.

18 August 2026
KazMunayGas H1 2026 financial results

Revenue +23.7% to 5,568 bln tenge; EBITDA +45% to 1,655 bln; net profit +69.1% to 904 bln; net debt rose to 983 bln tenge as cash/deposits declined.