INA boosts Adriatic gas output and installs Irena-3 platform

Key highlights
  • Ida C-4 DIR is producing about 165,000 cubic metres of gas per day after an investment of approximately EUR 65 million.
  • Combined output from Ida C-4 DIR, Ana-4 DIR and IKA JZ-6 DIR is approximately 340,000 cubic metres per day, 21% above forecast.
  • INA’s Adriatic gas production has risen from about 380,000 to 760,000 cubic metres per day since its drilling campaign began in 2025.
  • Gas from the Irena-3 platform is expected in the first quarter of 2027, via an eight-kilometre subsea pipeline to Izabela North.
Related projects For subscribers
Milestones, plant data, involved companies (owners, investors, licensors, contractors) and news — kept up to date.
INA North Adriatic five-well gas development drilling campaign
Under Construction
2026-07-20
2026-07-20
—
—
Energean–INA Irena gas field development, northern Adriatic
Under Construction
2025-07-30
2025-07-30
2025-11
—
Operational / Completed · expected date for subscribers

Adriatic well output

INA has completed drilling and well completion at Ida C-4 DIR in the northern Adriatic and tied it into the production system. The well is producing approximately 165,000 cubic metres of gas per day. The EUR 65 million well is the third in the company’s ongoing drilling campaign; extended testing began 18 days after drilling was completed.

Combined production from Ida C-4 DIR and the two earlier wells, Ana-4 DIR and IKA JZ-6 DIR, is about 340,000 cubic metres per day, 21% above the initial forecast. Including contributions from other projects, Adriatic production has increased from approximately 380,000 cubic metres per day before the campaign began in 2025 to 760,000 cubic metres per day.

Irena-3 development

The Irena-3 platform, installed as part of a joint project with Energean, is the next step in developing Adriatic production. CROSCO’s Labin jack-up rig has started wellbore construction. An eight-kilometre subsea pipeline will connect the platform to Izabela North, with first gas expected in the first quarter of 2027.

Onshore exploration

In 2026, INA increased its interest in the SAVA-07 exploration block from 40% to 100% by acquiring Vermilion’s remaining stake. Four wells were drilled in the first exploration phase; the second phase is underway. The company also secured licences for the SAVA-10/1 and DRAVA-02/02 blocks, where exploration is planned over the next three years. Seismic acquisition in DRAVA-02/02 began in late October.

Source: INA

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time. See our Privacy Policy.

Related articles

15 December 2025
Uniper and Vermilion Extend Gas Supply Deal in Germany

Vermilion will supply Uniper with German natural gas for two years, enhancing energy security and portfolio diversification.

3 June 2026
MOL Group starts first gas production at ACG field

First commercial gas from non-associated reservoirs beneath and above existing oil layers; initial well drilled from West Chirag; up to 4 Tcf estimated; gas to Sangachal via existing infrastructure.

8 May 2026
MOL Group Q1 2026: USD 212m profit amid supply disruptions and price controls

Higher hydrocarbon prices lifted upstream; production 95.5 mboepd. Downstream hit by lower refining volumes and feedstock scarcity; Rijeka delayed coker opened. Consumer services and circulars rose.