Evonik supplies Liocel adsorbent for Neptune Energy's Altmark DLE Pilot Phase II

Key highlights
  • Altmark resource estimated at 43 million tonnes lithium carbonate equivalent (LCE).
  • Fraunhofer IEG pilot plant operates oxygen-free and can process up to 1,000 litres of geothermal brine per day.
  • Evonik's Liocel® adsorbent selected as the first material for Pilot Phase II and will be supported with on-site application and process know-how.
  • Pilot Phase I evaluated ion-exchange and adsorption and selected adsorption technology for further investigation.
Related project For subscribers
Milestones, plant data, involved companies (owners, investors, licensors, contractors) and news — kept up to date.
Neptune Energy Altmark Lithium Extraction Project (ALE) · Germany
FEED / Pre-FID
2024-04
2024-11
—
—
—
Operational / Completed · expected date for subscribers

Project context

Neptune Energy is advancing the Altmark Lithium Extraction Project (ALE) to extract lithium from geothermal brine in Saxony-Anhalt, where a project-specific resource is estimated at 43 million tonnes of lithium carbonate equivalent (LCE).

Pilot Phase II and plant

Following Pilot Phase I, which evaluated ion-exchange and adsorption processes under Altmark-specific conditions and favoured adsorption, Pilot Phase II will test adsorption materials in a pilot plant developed by Fraunhofer IEG. The pilot plant enables oxygen-free lithium extraction and can process up to 1,000 litres of geothermal brine per day. Various adsorbent materials will be assessed over the coming months to support selection for potential industrial-scale deployment.

Evonik's role

Evonik Catalysts has been selected to provide its Liocel® adsorbent as the first material for evaluation after demonstrating stability and strong performance in preliminary testing, and will provide application and process know-how on-site. Michael Frey, Vice President and Head of Process Catalysts & Adsorbents at Evonik, said the company looks forward to further evaluating adsorption-based lithium extraction under the specific conditions of the Altmark resource.

Source: Evonik

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time.

Related articles

9 March 2026
Trafigura signs 10-year take-or-pay for 80,000 t battery-grade lithium carbonate from Smackover Lithium

Secures 8,000 tpa (80,000 t total) of battery-grade lithium carbonate from a US brine project using direct lithium extraction; FID expected 2026, first production targeted 2028.

6 January 2026
LibertyStream Produces Spec-Compliant Lithium Carbonate in Texas

Consistent lithium carbonate production validated; customer sampling underway. Plans for bulk sampling and offtake discussions aim for commercial volumes by 2027.

16 October 2025
E3 Lithium and Axens Sign MOU for Lithium Carbonate Sale and Sorbent Supply

The MOU outlines plans for E3 to supply lithium carbonate and Axens to provide a lithium sorbent, aiming for secure supply chains and future definitive agreements.