Sinopec sets record for deep shale oil drilling cycle
- The first 12 wells averaged a drilling cycle of 13.83 days; Feng Ye 1-8-B13HF took 11.68 days, a domestic record for continental shale wells deeper than 6,000 metres.
- A total of 36 wells are planned for the Minfeng 8 platform and will be developed in batches.
- An integrated three-rig system cut wellsite power load by two-thirds and labour by 30%; single-well investment fell 55%.
- The demonstration zone has reported 327 million tonnes of proven reserves and produced more than 2.2 million tonnes of oil.
Drilling performance
The first 12 wells at the Minfeng 8 well factory on Shengli Oilfield’s Jiyang shale oil platform averaged a drilling cycle of 13.83 days. Well Feng Ye 1-8-B13HF was drilled in 11.68 days, a domestic record for continental shale oil wells deeper than 6,000 metres.
Well factory operations
The site has limited surface space and complex underground conditions. The team arranged 36 wells for phased development and carried out drilling, fracturing and production in continuous operations. An integrated three-rig system reduced wellsite power load by two-thirds and labour by 30%. Drilling efficiency reached 75%, the drilling cycle was shortened by 82%, and single-well investment fell by 55%.
Demonstration zone
Established in 2022, the Shengli Jiyang shale oil national demonstration zone is China’s first national demonstration zone for shale oil in continental faulted lacustrine basins. It has reported proven reserves of 327 million tonnes and cumulative oil production of more than 2.2 million tonnes. The localization rate of core equipment has risen to over 95%.
Source: Sinopec