Cheniere Completes Corpus Christi Stage 3; 5,000th LNG Cargo Exported

Key highlights
  • CCL Stage 3 achieved substantial completion on August 28 with handover of the seventh and final train by Bechtel.
  • Cheniere issued full notice to proceed in June 2022 and saw first LNG from the first train in December 2024.
  • The project expands LNG production capacity by over 20%, to approximately 56 million tonnes per annum.
  • Cheniere loaded its 5,000th LNG cargo (Yari LNG) on August 29; the company has supplied over 340 million tonnes of LNG since 2016 and represents >10% of global capacity.
Related project For subscribers
Milestones, plant data, involved companies (owners, investors, licensors, contractors) and news — kept up to date.
Cheniere Corpus Christi Liquefaction Stage 3 · United States
Commissioning & Start-up
2022-06
2022
2026-08-28
—

Project completion

Corpus Christi Liquefaction Stage 3 (CCL Stage 3) reached substantial completion on August 28 when Bechtel Energy handed over care, custody and control of the seventh and final train to Cheniere. The Company issued full notice to proceed on CCL Stage 3 to Bechtel in June 2022, and first LNG production from the first train occurred in December 2024.

Production capacity

The Stage 3 works expand Cheniere’s liquefaction capacity by over 20%, increasing its U.S. Gulf Coast production capacity to approximately 56 million tonnes per annum.

Cargo milestone and exports

Cheniere marked its 5,000th exported LNG cargo with the loading of the Yari LNG, which departed Sabine Pass on August 29 en route to Asia. Since the company’s first cargo in 2016 it has supplied more than 340 million tonnes of LNG, and its platform now represents over 10% of total global LNG capacity.

Source: Cheniere

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time.

Related articles

13 April 2026
Honeywell to supply liquefaction technology for Rio Grande LNG Trains 4–5

NextDecade will use CWHE and C3MR via Bechtel to boost reliability, cut OPEX and increase LNG output from 18 to 30 MTPA; all five trains expected online by mid-2031.

5 February 2026
Chevron Announces Leadership Changes

Chevron announces retirements and new appointments in senior leadership roles, including Corporate Business Development, Supply & Trading, and Shale & Tight divisions.

29 September 2026
Cheniere and Petrobras agree 22‑year LNG SPA for 0.8 mtpa

0.8 mtpa FOB supply for 22 years; fixed‑fee cash‑flow visibility to support brownfield liquefaction growth and deliveries into the second half of the century.

12 August 2026
Cheniere: 10 Years of LNG Exports Highlighted in 2025 Corporate Responsibility Report

Marks decade since first Sabine Pass cargo; cites 330+ Mt supplied, nearly 5,000 cargoes, OGMP 2.0 Gold Standard and line of sight to 100+ mtpa by mid‑2030s.