Boliden Seeks EU Strategic Project Status for Nautanen

Key highlights
  • Nautanen copper deposit is 15 km from Aitik mine in central Norrbotten.
  • Potential annual production is 2-3 Mtonnes over a 20-year mine life.
  • Feasibility studies are ongoing; production may start in early 2030s.
  • EU Commission's assessment results expected in Q2 2026.

Project Overview

Boliden has applied to the European Commission to classify the Nautanen copper deposit as a strategic project under the Critical Raw Materials Act. Located in central Norrbotten, about 15 km northwest of the Aitik copper mine, Nautanen has potential for development as an underground mine.

Infrastructure and Environmental Considerations

The project aims to utilize existing industrial infrastructure at Aitik, such as the mill and tailings facility, to minimize environmental impact. Boliden plans to construct an entrance ramp to access the mine from a distance, further reducing the environmental footprint.

Production and Timeline

The conceptual annual production at Nautanen is estimated at 2-3 million tonnes, with a projected mine life of around 20 years. Feasibility studies are ongoing to finalize the operation details. Production is anticipated to begin in the early 2030s, contingent on obtaining necessary permits.

EU Commission Assessment

The European Commission is expected to announce the assessment results of the strategic project applications in the second quarter of 2026.

Source: Boliden

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time.

Related articles

12 August 2026
Boliden: Laver concession upheld after appeals rejected

Government rejected appeals, keeping the Laver concession intact; the deposit could double Sweden’s copper output and boost Europe’s copper self-sufficiency by about 10%.

4 March 2026
Boliden Kevitsa Initiates Change Talks Due to Finnish Mining Tax Increase

Finnish mining tax hike affects 285 jobs and halts a EUR 1 billion investment decision. Change talks to conclude in six weeks, impacting all 500 employees.

3 February 2026
Boliden Q4 2025 Report: Strong Metal Prices Boost Performance

Stable production, record mine profits, and strong metal prices marked Q4. Operating profit reached SEK 4,061m, with a proposed dividend of SEK 11.00 per share.

3 February 2026
Boliden's 2025 Mineral Resources and Reserves Update

Mineral Resources grew due to exploration and economic factors. Reserves varied by site, with notable changes in Aitik, Boliden Area, Garpenberg, Kevitsa, Tara, Somincor, and Zinkgruvan.

2 September 2025
Boliden Granted Mining Concession for Laver Deposit

The Swedish Mining Authority approved a concession for copper, gold, silver, and molybdenum extraction at Laver. Further exploration and permits are needed before investment.