Aurubis expects FY 2026/27 earnings below market expectations as Richmond ramp-up extends

Key highlights
  • Aurubis expects operating EBT of €430 million to €530 million in fiscal 2026/27.
  • Modifications to suspension components on all Richmond TBRCs will take around six months.
  • The technical ramp-up of the US plant is expected to be achieved in the second half of 2028.
  • Richmond is expected to make a negative earnings contribution in 2026/27, on par with the previous year.
Related projects For subscribers
Milestones, plant data, involved companies (owners, investors, licensors, contractors) and news — kept up to date.
Aurubis Richmond multimetal recycling plant, Augusta · United States
Commissioning & Start-up
2021-11
2021-11
2022-06
2025-09
Operational / Completed · expected date for subscribers
Aurubis Richmond Phase 2 capacity doubling, Augusta · United States
Commissioning & Start-up
2022-12-20
2022-12
2023
2026-08-06
Operational / Completed · expected date for subscribers

Richmond ramp-up revised

Aurubis will modify suspension-system components on all top blown rotary converters (TBRCs) at its Richmond, US plant. The work is expected to take around six months. The company now expects the plant’s technical ramp-up to be achieved in the second half of 2028.

While modifications are carried out, Richmond will process less recycling material than originally planned but will continue purchasing raw materials for Aurubis’ international smelter network. The site is expected to make a negative earnings contribution in fiscal 2026/27, on par with the previous year.

Earnings outlook

Aurubis expects operating earnings before taxes (EBT) of €430 million to €530 million in fiscal 2026/27, below current market expectations. Preliminary operating EBT for fiscal 2025/26 was €516 million, while IFRS consolidated EBT was €1,535 million.

Source: Aurubis

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time. See our Privacy Policy.

Related articles

6 August 2026
Aurubis raises full‑year outlook after stronger Q3 and major project progress

Group EBT and ROCE improved; Q3 outperformed prior quarters; large recycling plant started and ~90% of €1.7bn investment programme completed.

24 September 2025
Aurubis Opens First US Multimetal Recycling Plant

The new Georgia plant produces strategic metals, boosting US supply chain independence and creating 240 jobs, with plans to process 180,000 tons of recycling material annually.

7 October 2026
Aurubis expands Hamburg multimetal hub with automated pre‑processing facility

Automated sensor- and x‑ray-equipped plant to pre-process metal-bearing intermediates, improving valuation, safety and routing within the smelter network; due late 2028.

23 September 2026
Prysmian and Aurubis sign largest long-term copper wire rod supply agreement

Long-term deal secures copper wire rod supply, increases access to recycled low‑carbon copper and bolsters Europe’s capacity for electrification, energy infrastructure and AI.

3 July 2026
Aurubis opens Complex Recycling Hamburg plant for strategic metals

New unit processes copper, lead and sulfur in one plant, raising recycling capacity and EU supply-chain resilience.