Atyrau Refinery completes preventive maintenance and returns to operation

Key highlights
  • First oil received 8 July; phased commissioning began 1.5 days ahead of the RK Ministry of Energy schedule.
  • Plant now processes 16.2 Kt of oil per day and has refined 157 Kt of feedstock since resumption.
  • Since reaching operational mode the refinery shipped 35.3 Kt gasoline, 48.7 Kt diesel and 5.7 Kt LPG; fuel deliveries ongoing without delays.
  • PM included inspections of 20 reactors, 213 vessels, 32 columns and 231 heat‑exchange units; >335 tonnes of catalysts renewed; internal components of the CDU‑VDU‑3 vacuum distillation unit were replaced; ~1,700 specialists and 50+ special-purpose units were involved.

Return to operation

Following preventive maintenance, Atyrau Refinery reached operational mode. The first oil was received on 8 July and the phased commissioning of process units began 1.5 days ahead of the RK Ministry of Energy's schedule.

Production and shipments

The plant currently refines 16.2 Kt of oil per day and has processed 157 Kt of feedstock since resumption. Since process units reached operational mode, shipments total 35.3 Kt of motor gasoline, 48.7 Kt of diesel fuel and 5.7 Kt of liquefied petroleum gas. Fuel is being supplied without delays.

Maintenance scope and resources

During the preventive maintenance, mandatory technical inspections covered 20 reactors, 213 vessels, 32 columns and 231 units of heat‑exchange equipment; individual pipeline sections were replaced. More than 335 tonnes of catalysts were renewed and internal components of the vacuum distillation unit at CDU‑VDU‑3 were replaced to increase light product output. Approximately 1,700 specialists and over 50 units of special‑purpose equipment were involved in the operations.

Source: KMG

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time.

Related articles

9 July 2026
Rompetrol Rafinare Petromidia marks 50-year milestone

50-year anniversary of the Năvodari refinery; built on reclaimed land, now a 29‑unit complex with >5 Mtpa capacity, Nelson Complexity 9.32 and 2025 production records.

2 July 2026
Rompetrol Rafinare: APC digital control boosts Petromidia production and cuts costs

Automated process control increased high‑value product yields, lifted utilization to 98.1% and delivered estimated savings of over USD 2.5M in 2025.

29 May 2026
Rompetrol Rafinare Q1 2026: Turnover up 8%, net profit achieved

Q1: EBITDA $27.5M; March shutdown (700+ tasks) completed; Petromidia processed ~1.2Mt, white product yield 83.76%; domestic fuel share 66%; state contribution $577M

14 August 2026
Rompetrol Rafinare posts solid H1 2026 results

Consolidated turnover +25% to USD 3.5bn; EBITDA +65% to USD 128.1m and net profit USD 40.4m. Petromidia shifted output toward domestic market; H2 outlook cautious.

15 May 2025
Rompetrol Rafinare Q1 2025 Operational Growth

Turnover rose 21% to $1.3B, despite a 30% EBITDA drop. Fuel sales grew, exports hit $407M, and state contributions increased to $372M. LDPE plant restarted, boosting petrochemical output.