Greenlight Electricity Centre Limited Partnership is a Canadian limited partnership formed as the owner and developer of the Greenlight Electricity Centre, a 932 MW combined-cycle natural gas-fired power generation project in Sturgeon County, Alberta, within the province’s Industrial Heartland.

Read more

The facility is designed with carbon capture readiness and permitted for phased modular expansion to a total capacity of 1,864 MW. It will supply dedicated behind-the-fence power to a co-located hyperscale data center campus under a long-term Electrical Energy Supply Agreement structured as a tolling arrangement. The plant is expected to require approximately 150 MMcf/d of natural gas, with transportation secured through existing pipeline systems, and targets commercial operations in the second half of 2030 at a total project cost of approximately $4.6 billion.

Ownership consists of Pembina Pipeline Corporation (47.5%), Morgan Stanley Infrastructure Partners (47.5%), and Kineticor Asset Management (5%). Pembina acts as construction and operations manager, leveraging its infrastructure expertise, while Kineticor, the original developer, provides ongoing support. The partnership is distinct from the data center it serves and focuses on delivering reliable, dispatchable baseload power to meet growing electricity demand in Alberta’s energy and technology sectors.

Also known as Greenlight Electricity Center Limited Partnership, Greenlight Electricity Centre LP, and GLEC.

The project Greenlight LP is involved in

chemXplore tracks 1 project involving Greenlight LP, of which one is active.

Greenlight Electricity Centre 932 MW combined-cycle plant, Alberta
  1. Announced / Concept
  2. FEED / Pre-FID
  3. FID / Sanctioned
  4. Under Construction
  5. Commissioning & Start-up
Phase
Under Construction
Where
Canada
Makes
Natural gas , Carbon dioxide
Partners
Kineticor , Morgan Stanley Infrastructure Partners , Pembina

Greenlight LP in chemical industry news

30 July 2026
Técnicas Reunidas consolidates growth as Middle East and data‑centre power lift results

Q2 EBIT €73m (5% margin); H1 orders €6bn and backlog €14bn; >€5bn UAE sole‑contract win; Greenlight gas+CCS plant to power a META data centre; guidance above €6.5bn revenue.

10 July 2026
Técnicas Reunidas wins 932 MW Alberta power plant for META data centre

Consortium to build a 932 MW combined‑cycle gas plant in Alberta to power META’s large AI data centre; plant will include carbon capture and can be doubled to 1,864 MW.

Where its projects are