Key highlights
Unplanned Outage
Huntsman Corporation is dealing with an unexpected outage at its Polyurethanes facility in Rotterdam, Netherlands. This incident affects the larger of the two MDI production lines.
Financial Impact
The outage is projected to negatively impact the fourth quarter 2025 adjusted EBITDA by approximately $10 million. As a result, the adjusted EBITDA is now expected to be at the low end of the previously communicated $25 million to $50 million range.
Production Resumption
Production at the affected MDI line is anticipated to resume by mid-December, allowing the facility to return to its normal operations.