Eni commissions 120 MW gas plant in Kazakhstan’s Mangystau hybrid project
- The 247 MW project is being developed in Kazakhstan’s Mangystau Region by Eni, KazMunayGas and Plenitude.
- The 120 MW gas plant was commissioned after 12 months of construction, involving 3 million man-hours without a lost-time injury.
- The 50 MW solar plant was commissioned in September 2025; the gas plant reached first industrial electricity in July 2026.
- Construction of the 77 MW wind plant is next, with commercial operations scheduled to begin in 2027.
Project commissioning
Eni has commissioned a 120 MW gas power plant in Kazakhstan’s Mangystau Region. It is part of the 247 MW Mangystau Hybrid Power Plant Project, developed with KazMunayGas and Plenitude. The project integrates solar and gas generation, with wind power planned as a later phase, to supply power to KazMunayGas subsidiaries in the region.
Construction and commissioning took 12 months and involved 3 million man-hours without a lost-time injury. The plant reached first industrial electricity in July 2026 and is ready for operation by a KazMunayGas affiliate.
Remaining development
The project’s 50 MW solar plant was commissioned in September 2025. Work will now focus on a 77 MW wind plant. Most field civil works are expected to be completed by 2026, allowing installation of the first wind turbines. Commercial operations are scheduled to start in 2027, completing the hybrid configuration.
Source: Eni