Elkem invests NOK 260m to replace furnace at Elkem Rana

Key highlights
  • NOK 260 million approved to replace one of two furnaces and its off-gas equipment at Elkem Rana.
  • Installation is scheduled to start in the first quarter of 2027 while the plant's second furnace continues normal operation.
  • Elkem Rana produces approximately 80,000 tonnes of ferrosilicon and 15,000 tonnes of Microsilica annually across its two furnaces.
  • The new furnace is designed to improve operational reliability, energy efficiency, reduce dust and process emissions, and facilitate increased use of biocarbon.

Investment and scope

Elkem ASA has approved NOK 260 million to replace one of the two furnaces and the associated off-gas equipment at its Elkem Rana plant in Northern Norway. The existing off-gas equipment has reached the end of its operational lifetime.

Timing and operations

Installation of the new furnace is scheduled to start in the first quarter of 2027. The plant's second furnace will remain in normal operation during the installation to maintain production.

Technical objectives

The upgraded furnace will incorporate Elkem's latest proven technology to enhance operational reliability, process control and energy efficiency. It is also designed to further reduce dust and process emissions and to enable increased use of biocarbon in support of the company's climate ambitions.

Production and markets

Elkem Rana is a leading European ferrosilicon plant and supplier to steel, foundry and metallurgical industries. Across its two furnaces the plant produces about 80,000 tonnes of ferrosilicon and 15,000 tonnes of Microsilica annually.

Source: Elkem

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time.

Related articles

22 September 2026
Elkem awarded 1.3 million extra EU ETS allowances for 2021–2025

Follows Norway's finding that domestic producers were under‑allocated versus EU peers; five plants to receive EU‑aligned allocations for 2026–2030.

10 July 2026
Elkem Q2 2026 results: cost reductions and balance‑sheet strengthening

EBITDA fell on weak silicon prices; raised NOK 1.8bn, refinanced EUR 1bn facility and obtained NOK 750m NIB loan; Elkem Iceland reclassified as discontinued.

2 July 2026
Elkem appoints Dag Teigland as CEO; Helge Aasen to chair the board

Leadership change effective 3 August 2026; incoming CEO returns with industrial and investment experience and prior Elkem roles; outgoing CEO moves to board chair after 17 years.

28 April 2026
Elkem wins NOK 87m from Enova to scale biocarbon use in silicon production

Project (total NOK242m, 2026–28) will test industrial biocarbon across labs, pilots and five smelters to double biocarbon share (from ~25%) by 2030, potentially cutting up to 0.5 Mt CO2/yr

20 April 2026
Elkem sells Saguenay biocarbon unit to CHAR Tech, secures 5‑year 62,500‑t supply